Demand response is a paid arrangement in which a large electricity user agrees to cut load when the grid operator asks.

Put it to work Hosting versus home Running a machine at home against hosting it. Open the page
Paid for
Being ready and for reducing load
Asked by
A grid operator or a utility
Entered through
An approved market participant
Proved with
Interval meter data
Measured against
An agreed baseline

What it means in practice

The participant is typically paid for standing ready and again for the load it actually sheds. In ERCOT, sites enrol through a Qualified Scheduling Entity and products differ by how fast the load must drop, from seconds for Responsive Reserve Service to 30 minutes for Non-Spin. Miners suit these programmes because they can drop to near zero almost instantly and nothing is lost but mining time.

Why miners are good at it

A grid must balance supply and demand every second. Most factories cannot stop in seconds without spoiling something; a mining site can, and starts again just as quickly. That makes it a useful partner on a hot afternoon or a cold night.

The site is paid for being ready and for the load it sheds. Between events it simply mines.

From enrollment to settlement

A site first shows what it can drop and how fast, often with a test. It signs up a number of kilowatts for a season, month or day. When the operator calls, the site reduces and holds until it is released. Afterward the meter data is compared with a baseline and the payment is calculated.

The baseline is the estimate of what the site would have used without the call. A steady load makes it easy to agree on. A mining hall that draws the same power all day is close to ideal here.

Emergency, economic and reserve programs

Emergency programs call rarely and expect a firm response. Economic programs let a participant offer load at a price, so the market calls it when prices are high. Reserve products hold capacity ready to act within seconds or minutes, some of them triggered automatically by a relay when grid frequency drops.

The faster and more reliable the response, the more it is usually worth, and the stricter the proof.

One load cannot normally be sold twice for the same hour. Choosing between programs is part of running a flexible site.

Voluntary public appeals on television are something else again. They carry no payment and no penalty, and many sites answer them anyway.

A month on paper

Example figures: a site offers 1 MW for 700 hours at $6 per MW for each hour of readiness. That is $4,200. It is called once, for four hours, and stops mining worth $40 per MWh after power, so it gives up $160. The program also pays $50 per MWh for the energy not used, another $200. The month adds $4,240 net.

In a month with no call the readiness payment stands alone. In a month with many, the hours given up matter more, which is why the limit on calls is an important line in the contract.

What a customer of the site notices

A short, shared dip in hashrate, then normal running. The site runs the program, carries the obligation and answers for a missed call. The hosting agreement states how those hours are recorded and where any payment goes.

Someone mining at home can meet the small version: a utility program that rewards lower use on request, through a smart plug or an app. The terms are the utility’s own.

Worked example

A 2 MW block is dispatched for 3 hours, shedding 2 × 3 = 6 MWh. If the forgone mining margin is $40 per MWh, the site gives up 6 × 40 = $240 of margin, which the programme's availability and performance payments must exceed for the event to pay.

Example figures, not live data.

Step by step

  1. Confirm how many kilowatts can drop, and how quickly, with a timed test.
  2. Check that the meter records in the interval the program needs.
  3. Enroll through the market participant that represents the site.
  4. Automate the response and keep a manual fallback.
  5. After each event, compare the meter data with the settlement.

Common mistakes

  • Offering the nameplate load when part of the fleet is usually off.
  • Relying on a person to answer a ten-minute call at night.
  • Forgetting that cooling equipment keeps drawing power for a while after the machines stop.

Common questions

Is demand response the same as curtailment?

Curtailment is the act of using less power. Demand response is one reason for it: an agreement that pays for doing so on request.

Does stopping hurt a miner?

A clean stop through the firmware does not. Frequent hard power cuts are harder on power supplies, which is why sites stop hashing first.

Can a small miner take part?

Through an aggregator or a utility program in some areas. Direct participation usually needs a larger load.

What happens if a site does not respond?

The program’s terms apply, which can mean a reduced payment or a penalty. That is why sites test and automate.

How often are events called?

It varies by program and season. Emergency products may go a year without a call; economic ones may run weekly.