Power and wiring

PDU (power distribution unit)

A PDU is a rack-mounted unit that takes power from one or more large circuits and splits it into outlets for individual machines.

Put it to work Hosting versus home Running a machine at home against hosting it. Open the page
Sits between
the breaker panel and the machines
Types
basic, metered, switched, metered by outlet
Usual outlets
C13, C19 or a mix
Mounting
upright along the rack or flat across it
Plan with
80% of its rating for a load that never stops (US practice)

What it means in practice

Mining PDUs are built for high continuous loads, often fed by 240 V single-phase or by three-phase supplies, and many meter each outlet. Metered outlets let a host bill each machine on what it actually used. Matching the PDU's outlet type, such as C19, to the miners' power cords avoids adapters.

Choosing a PDU for miners

Match four numbers: the input plug and phase your electrician provides, the total current, the outlet type and count, and the breaker behind each group of outlets. Keep the total at 80% of the rating, because miners draw their full current all day.

A PDU with metering shows every machine’s kilowatt-hours. A switched one restarts a machine without walking to the rack.

Inside the housing

A PDU has an input cable, a set of outlet groups and often a small breaker for each group. On a three-phase unit the groups take turns: group one between phase A and neutral or between A and B, group two on the next phase, and so on. The colors or letters printed beside the outlets show which group is which.

That order decides where each machine goes. Filling the unit from top to bottom without looking loads one phase to its limit while another sits empty.

A three-phase rack worked through

Example figures: a PDU fed with 415 V three-phase and rated 60 A. Continuous power is √3 × 415 × 60 × 0.8 = about 34.5 kW. Machines of 3,500 W take 14.6 A each from a 240 V outlet group.

34.5 ÷ 3.5 gives nine machines, three on each phase. Every phase then carries 3 × 14.6 = 43.8 A, under the 48 A that 80% of 60 A allows. A tenth machine would push one phase to 58.4 A, so nine is the answer although the unit may have twelve outlets.

What each extra feature is good for

Metering on the input shows the total and the balance between phases. Metering on each outlet shows every machine, which is what fair billing in a shared space needs. Switching lets you restart one machine from a desk, and start a row in steps so the inrush does not trip the feeder.

Environmental ports take a temperature probe. Placed at the intake side of the rack it tells you about a blocked filter before the machines slow down.

Heat, cords and the place it hangs

A PDU at the exhaust side lives in hot air. Check its ambient rating: many are made for 45 or 60 °C, and mining exhaust can pass the first figure in summer. Mount it at the cooler edge or choose the higher rating.

Locking cords or retaining clips stop a plug from working loose under fan vibration. A plug that sits half out heats at the contact, and that spot is the one to check with a thermal camera during the first week. Have the feed itself installed by a licensed electrician.

Worked example

A planner who limits continuous load to 80% of a 30 A, 240 V circuit has 30 × 0.8 × 240 = 5,760 W available. One 3,500 W miner (about 14.6 A) fits; two (about 29.2 A) do not.

Example figures, not live data.

Step by step

  1. Write down the supply: voltage, phases and breaker.
  2. Work out 80% of the PDU’s rating in amps for each phase.
  3. Divide by the current of one machine, at its highest power mode.
  4. Count outlets, and check the breaker behind every outlet group.
  5. Spread the machines over the phases and read the meter after an hour.

Common mistakes

  • Counting outlets instead of amps.
  • Plugging a second PDU into the first to gain sockets.
  • Ignoring the group breaker: two machines on one 20 A group trip it even when the unit as a whole has room.

Common questions

Is a PDU the same as a power strip?

It does the same job on a larger scale: higher voltage and current, locking outlets, breakers inside and mounting for a rack.

How many miners fit on one 30 A PDU at 240 V?

It may carry 24 A all day, or 5,760 W. That is one full-size machine, with room for a smaller one.

Vertical or horizontal PDU?

Vertical units run along the rack, have many outlets and keep cords short. Horizontal ones take rack height and suit a few machines or a network shelf.

Can a PDU power both miners and network gear?

Yes, if it has outlets for both. Many sites give switches a feed of their own, so a tripped miner does not take the network down with it.

Does a PDU protect against surges?

Some have surge protection built in, many do not. At a site it is normally fitted at the main panel.